The measure is the raised floor

17/08/2015

 1 / Preparation: Unity textures and drawings.

• Get detailed drawings of the device on the floor, electrical socket location, device location, detailed structural drawing walls, windows, doors .... approved from Investor.
• Acquisition of premises, mold field, the axis positioning and scope of works. The milestone was marked, preserved by paint. Newsletter ground delivery records.
• As the venue was renovated ground so note the position of the door is opened or open on ?. Shops in position on the floor or under the floor?. Combined with the design reviewed all eye problems exist and propose the settlement.
• Contact unit building management and related units for permission to use the public transport, power, water resources, as well as coordinate the work of maintaining common security.
• Arrange staffed 24 / 24h for self preservation materials, construction materials.
• Prepare 02 extinguishers on site
• Preparation of construction tools and supplies.
• To collect materials to construction sites.
2 / Step 1: Clean the entire system of industrial flooring
• Carry out cleaning clean the residual material on the floor.
3 / Step 2: Determine the required height of systems engineering and technical exchanges
• To conduct measurements, determine the height of the raised floor at the starting position.
• The height of the raised floor is determined and maintained throughout the construction process by balancing machine dedicated laser.
• Ensure that the underfloor systems after construction is not affected by altitude floors and floor maintaining air circulation system below ground.
• For the position of doors, to ensure the transportation of equipment and travel convenience, the room doors are made up and down steps or slopes podium.
4 / Step 3: Divide the box and determine the base location:
• After you have identified as the design height, will continue to locate the cellular base by directly trenmat floor and marking ink to the base paste the position of the base is not moved. Brackets are divided by the texture is 600x600mm
• Put the concrete base floor with special glue.
• The calibration floor to reach the height needed will be made by increasing or decreasing the base flange threaded through flexible system structure of the stand.
5 / Step 4: Install the horizontal supports of the system:
• Support bar horizontal effects evenly distributed bearing capacity of the floor plate and suppress the movement of the system. After pasting the base using glue, we will carry out the installation of the horizontal support bar, in accordance with standards and structures.
      - Horizontal bar steel support plate is bolted to the steel foot to measure constitutes a leg - pulling tightly linked.
      - Brackets and braces are glued rubber sealing (gasket) and fixed noise floor system
     - Installation of the guarantee not to cause trouble breaking or cracking of the floor tile flooring.
6. / Step 5: Mounting surface slab
• The installation of the floor plate surface will be carried out after the complete execution the base and the horizontal bar. For those suffering material plate is placed directly on the base and supports.
• For the sheet is cut by the size of the room, after mounting the panels are cut to insert silicon glue sealing the exposed location between the floor and wall.
• Installation of floor plate to complete even where there.
• After installing the entire floor is finished we will conduct a flat pick and test system was last broken circuit
7 / Step 6: Cut holes for mounting electrical boxes / network audio floor.
• Cut the hole to size requirement at the location specified by the investor and approved.
8. / Step 7: Finishing flooring systems
      - Clean the floor before handing over to the investor.
      - Guide Investor usage and preservation techniques to maintain flooring durability and reliability of the floor.
      - Manual lifting floorboards hand.

Nam Hoa Phat supplying raised floor installation, technical flooring, raised floor .... With a team of skilled technicians, experienced in many projects such as Techcombank, Vietcombank, Agribank, Plant Hyosung, Office CJ, Plant Ainomoto ... Nam Hoa Phat always bring quality projects and dedicated service.
For further information please contact:
Engineering Company Limited Nam Hoa Phat
Address: F13 / 2G, Road Union 5-6 Ap, Ap 6A, Vinh Loc, Binh Chanh, HCMC
Telephone: 08.6678.6605 - Hotline: 090101.9805 - Email: Info.namhoaphat@gmail.com
Website: Namhoaphat.com.vn